N E W   C O N S T R U C T I O N   A C T I V I T I E S   A N D  G R E E N   B U I L D I N G   P R O G R A M

ECONOMIC ACTIVITY GENERATED FROM NEW BUILDING CONSTRUCTION

PERIOD COVERPERMITS ISSUED
(New Construction)
ESTIMATED BUILT-UP AREA
(in sq.m.)
CONSTRUCTION COST
(@Php 12,000/sq.m.)
(in Php Million)
PROJECTED REAL ESTATE
(in Php Million)
-(a)-
ESTIMATED ECONOMIC GENERATED  (Multiplier Effect)
(in Php Million)
-(b)-
DIRECT LABOR GENERATED
-(c)-
UPSTREAM WORKFORCE  (1 person / Php 1M material cost)
-(d)-
20151,4441,846,82422,161.89166.21110,809.4573,87313,297
20161,4322,178,05326,136.64196.02130,683.1987,12215,682
20171,6032,282,13327,385.60205.40136,927.9991,28516431
2018 (as of August)1,1841,846,80022,161.60166.21110,808.0073,87213,297
Total56638,153,81097,845.73733.84489,229326,15258,707
  • Construction Cost x 30% x 0.025
  • 5 x Construction Cost (based on the Associated General Contractor of America)
  • (40% x Costruction Cost) / (300 days x Php 400)
  • (60% x Construction Cost) / Php 1M

GREEN BUILDING, STATUS OF APPLICANTS (as of August 2018)

APPLICATION TYPENO. OF APPLICATIONSW/ BUILDING PERMITW/ SUBMITTED PRELIMINARY MANDATORY REQUIREMENTS (ON GOING)W/ PRELIMINARY CERTIFICATEW/ SUBMITTED FINAL MANDATORY REQUIREMENTS
(ON GOING)
W/ FINAL CERTIFICATE
BPFP
Commercial Buildings229108174661477621
Institutional Buildings5625423024202
Industrial Buildings392235829181
Voluntary Applications4143110
Total32815625510720111524
  • Under the City’s Green Building Program, a total of 328 buildings were already evaluated in compliance to the Green Building Ordinance, 255 of which were already issued with Building Permit, 201 Green Building Preliminary Certificate, and 24 with Green Building Final Certification.